Custom scheduling tools and databases – Part IV (Final)
- Task Name – Regular WBS Task Name. PMO_Resource-TO Do Tasks is grouped by week the task should begin. PMO_Resource-Incomplete Tasks is grouped by the week the task should be completed.
-
Start – Date the task is to begin.
-
Finish – Date the task is to be completed.
-
Accountable (CF) – I added this column because there were several resources for the majority of tasks and it was unclear who had final authority for task decisions and completeness.
-
Resource Names – Individuals assigned and “responsible” to achieve the task.
- Task Name – Regular WBS Task Name grouped by when the task should be completed.
- Task Issues (CF) – This field is to capture issues affecting task completion. This field is typically filled induring updates to the schedule using the PMO_Tracking Gantt view. Use this field to describe the cause of the issue. These should be escalation issues meaning you have to go outside the project team for resolution. This field is NOT for describing general task status.
- Accountable (CF) – I added this column because there were several resources for the majority of tasks and it was unclear who had final authority for task decisions and completeness.
-
Status – This is an MS Project generated indicator which can be sometimes misleading. The Status field indicates the current status of a task, specifying whether the task is Complete, On Schedule, Late, or a Future Task based on the MS Project algorithm. The trouble with this is that you can begin a task ahead of schedule (good) then fall behind on this task (bad) meanwhile the task Status will read Future Task (due to the baseline) which is no longer true. This is why I’ve added the next custom field…
- Slipping Tasks (CF) – This field calculates whether a task is slipping based on the baseline or actual start if started early then gives you an indicator based on the number of days the task is behind schedule; Yellow 1-10 days late, Red 11-20 days late, Black >20 days late. If completed the status changes to Green (100% complete).
- Actual Duration – Number of days actually spent on task.
- Rem(aining) Dur(ation) – Number of days left to complete task.
- Actual Start – Date the task was started.
- Finish – Scheduled finish date of task.
-
Baseline Finish – Scheduled baseline finish of task.
-
Status Indicator – The Indicators field displays indicators that give different types of information about a task. Go to the link for more details.
-
Task Name – Regular WBS Task Name.
-
Duration – Duration used by MS Project for calculating schedule.
-
Start – Planned start date of task.
-
Finish- Planned finish date of task.
-
Accountable (CF) – I added this column because there were several resources for the majority of tasks and it was unclear who had final authority for task decisions and completeness.

Fig. 6 Microsoft Project template PMO_Gantt Chart screen shot
The last view is the typical (Yawn!!!) PMO_Gantt Chart. I add it here for historical purposes only and because if I didn’t people would continually ask “Where’s the Gantt Chart?” I can’t tell you the number of times I’ve asked someone for their project plan (not schedule) and they pull out a 20 page stack of this nonsense. Who looks at this stuff? Not management! The first thing this tells me, if this is all they give me, is that the person running this project doesn’t really understand project management only how to operate MS Project (or whatever software used to create it). This is the reason why I’ve developed and used the previously described views and templates in order to initiate, plan, execute, monitor and control my projects.
This post captured the last six views discussed in this series. As shown with the various views we’ve created a pretty wide-ranging project database, used various views for inputting information and using the same data in different output views for communication and status. This should give you the idea that you have very specific requirements and data needs for your projects. Extend your database a little farther in your project. Take Project and add one or more custom fields and views to capture that information as it relates to tasks or resources or some other aspect of your project and keep your project info current and concise.
If you would like the MS Project file with all views already included send me an email with your request to wayne@all3pm.com and I will forward a copy to you. Any feedback you care to provide is greatly appreciated.
Thanks for following…